TESTING & COMMISSIONING (T&C) OF HVAC CHILLER

TESTING & COMMISSIONING (T&C) OF HVAC CHILLER ✅ Pre-Commissioning Checks ✔ Verify chiller model, capacity, refrigerant, and installation as per approved drawings. ✔ Check foundation alignment, vibration isolators, and mounting bolts. ✔ Confirm piping connections (CHW & Condenser Water) — flow direction, supports, flexible joints. ✔ Ensure valves installed correctly: isolation, balancing, flow switch, drain, vent. ✔ All electrical connections terminated — proper cable size, breaker, earthing, and isolator. ✔ Sensor wiring & BMS points connected and tested. ✔ Insulation completed and cladding sealed (especially outdoors). Flushing & Cleaning ⇒ Conduct chemical flushing of CHW & condenser lines: Use biocide + scale remover. Flush till water is clear. ⇒ Post-flush: Passivation to protect pipe interiors. ⇒ Hydrostatic pressure test as per code (usually 1.5x working pressure). ⇒ Vent all air pocke...