Skip to main content

TESTING & COMMISSIONING (T&C) OF HVAC CHILLER

TESTING & COMMISSIONING (T&C) OF HVAC CHILLER



✅ Pre-Commissioning Checks

✔ Verify chiller model, capacity, refrigerant, and installation as per approved drawings.

✔ Check foundation alignment, vibration isolators, and mounting bolts. 

✔ Confirm piping connections (CHW & Condenser Water) — flow direction, supports, flexible joints. 

✔ Ensure valves installed correctly: isolation, balancing, flow switch, drain, vent. 

✔ All electrical connections terminated — proper cable size, breaker, earthing, and isolator. 

✔ Sensor wiring & BMS points connected and tested. 

✔ Insulation completed and cladding sealed (especially outdoors).


Flushing & Cleaning

⇒ Conduct chemical flushing of CHW & condenser lines: 

  •  Use biocide + scale remover. 

  •  Flush till water is clear.

 ⇒ Post-flush: Passivation to protect pipe interiors. 

⇒ Hydrostatic pressure test as per code (usually 1.5x working pressure). 

⇒ Vent all air pockets using manual/auto air vents.


Dry Run / No Load Test

⇒ Power up the panel — check phase sequence, voltage levels, and alarms. 

⇒ Run chilled water pumps (primary/secondary). 

⇒ Confirm flow switch operation (cut-in/cut-out). 

⇒ Run chiller without load: 

  • Compressor starts/stops. 
  • No abnormal vibration/sound. 
  • Monitor electrical readings (Amps, Volts).

❄ Full Load Commissioning

⇒ Start system with actual cooling load (or dummy load if building not ready). 

⇒ Monitor: 

  • CHW Supply & Return Temperature (Target Δ T = 6–8°C)
  •  Condenser In/Out Temperature
  •  Compressor amps and running condition 
  • Refrigerant pressures (low & high side) 
⇒ Check expansion valve response and superheat. 

⇒ Verify auto-cutoff & restart at setpoints (thermostat, overload, flow).


Functional & Safety Tests

⇒ Simulate flow loss — ensure chiller trips. 

⇒ Simulate high/low pressure — verify safety shutdown. 

⇒ Trip power — confirm auto-restart sequence. 

⇒ Test BMS integration: 

  • Start/Stop control 
  • Alarm signals 
  • Temp/Pressure monitoring 
  •  Status feedback

Comments

Popular posts from this blog

VALVES USED IN A CHILLER SYSTEM AND THE TYPICAL VALVE PACKAGE

  VALVES USED IN A CHILLER SYSTEM AND THE TYPICAL VALVE PACKAGE 1.Chilled Water Side Valves ⇒Isolation valve (manual/electric actuated). ⇒ Installed on CHW supply and return lines.  ⇒ Used to isolate chiller for maintenance. 2. Balancing Valve (Manual or Automatic)  ⇒ Ensures correct flow rate to/from chiller.  ⇒ Helps maintain Delta T and proper flow distribution.  ⇒ Located after evaporator outlet (return line). 3. Differential Pressure Bypass Valve (if 2-way valves in system)  ⇒ Prevents excess pressure build-up when terminals shut.  ⇒ Maintains flow through chiller. 4. Flow Switch  ⇒ Senses chilled water flow across evaporator.  ⇒ Safety interlock: trips chiller if flow is lost.  ⇒ Usually paddle type or electronic. 5. Air Vent Valve (Manual or Automatic)  ⇒ Removes air pockets.  ⇒ Placed at high points of piping and chiller headers. 6. Drain Valve  ⇒ For flushing, cleaning, and maintenance.  ⇒ Located at low poin...

HVAC MEP Thumb Rules & Formulas (With Examples)

  HVAC MEP Thumb Rules & Formulas (With Examples) 1. Heat Load Calculation  Formula: Q = Area (sq.ft) x Heat Load Factor (BTU/hr per sq.ft) Example: 500 sq.ft office: Q = 500 x 30 = 15,000 BTU/hr TR = 1.25 2. CFM Calculation Formula: CFM = Sensible Heat (BTU/hr) / (1.08 x Delta T) Example: 12,000 BTU/hr, Delta T = 20°F CFM = 556 3. AHU/FCU Sizing Rule: 1 TR = 400 CFM 2 TR Airflow = 800 CFM 4. Duct Sizing Velocity Limits: Main: 1400-1800 FPM 800 CFM @ 1000 FPM 0.8 sq.ft 14"x10" 5. Chilled Water Flow Rate Formula: GPM = BTU/hr / (500 x Delta T) Example: 24,000 BTU/hr GPM = 4.8 6. Pipe Sizing 1" pipe: 8-12 GPM 2" pipe: 30-40 GPM 35 GPM Use 2" 7. Chiller Sizing Formula: TR = BTU/hr / 12,000 Example: 60,000 BTU/hr → 5 TR 8. Cooling Tower Sizing Rule: Heat Rejection = 1.25 x Load 10 TR → Tower = 12.5 TR 9. Pump Head Calculation Formula: Power (kW) = (Q x H x 9.81) / (Efficiency x 1000) Example: Q = 5 L/s, H = 20 m, Efficiency = 0.75 Power 1.31 kW 10. Fresh Air Re...

Type of Heat Exchanger

 There are several types of heat exchangers used in HVAC systems, including: 1. Coil Type:     - Chilled water coils     - Hot water coils     - DX (direct expansion) coils     - Evaporator coils     - Condenser coils 2. Shell and Tube Type:     - U-tube heat exchangers     - Straight tube heat exchangers 3. Plate Type:     - Plate and frame heat exchangers     - Plate and shell heat exchangers 4. Finned Tube Type:     - Finned tube heat exchangers 5. Spiral Type:     - Spiral heat exchangers 6. Regenerative Type:     - Regenerative heat exchangers 7. Adiabatic Type:     - Adiabatic wheel heat exchangers 8. Run-Around Coil Type:     - Run-around coil heat exchangers These heat exchangers are used in various applications, including: - Air conditioning - Heating - Ventilation - Refrigeration - Heat recovery - Industrial processes Each type of hea...