Chiller Installation Requirements
Chiller Installation Requirements.
1. Foundation & Mounting
⇒ Concrete Plinth/Base:
- Should be flat, leveled, and minimum 150 mm above FFL.
- Designed to take dead load + dynamic load of the chiller.
- Ensure plinth length/width matches OEM mounting dimensions.
⇒ Vibration Isolators:
- Use spring isolators or neoprene pads below the chiller to reduce vibration and structure-borne noise.
- For rooftop units, include seismic restraints if required by local codes.
⇒ Chilled Water Lines
- Inlet & Outlet properly labeled.
- Use flexible rubber bellows at inlet/outlet to absorb vibration and thermal expansion.
- Provide isolation valves, y-strainer, and flow switch.
- Install thermometers & pressure gauges at inlet and outlet for monitoring.
- Ensure correct pipe supports as per spacing schedule to avoid sagging.
⇒ Condenser Water Lines (for water-cooled only)
- Similar provisions as above.
- Ensure proper sloping and venting.
- Include chemical dosing point, bleed line, and auto bypass if needed.
⇒ All chilled water pipes must be insulated with closed-cell elastomeric foam (min. 19 mm–25 mm).
⇒ Properly sealed joints and vapor barrier to avoid condensation.
⇒ For outdoor pipes: UV-resistant cladding (aluminum or PVC) to protect insulation.
4. Air Clearance & Accessibility
⇒ Maintain manufacturer’s recommended service clearance:
- Typically: 1.5–2.0 m on sides for maintenance.
- Overhead clearance for removing compressor/heat exchanger tube bundles.
⇒ Ensure safe access ladders, platforms, or walkways if rooftop-mounted.
⇒ No obstructions around air-cooled condensers — at least 1.5 m air clearance on all sides.
⚡ 5. Electrical Power Supply
⇒ Provide dedicated MCC/Panel for the chiller.
⇒ Size power cable, isolator, and breaker as per full-load amps + starting current.
⇒ Include:
- Remote start/stop
- Earthing/Grounding
- Cable tray support
- Overload and short circuit protection
⇒ Power supply must be stable voltage (±5%) and have phase sequence monitor.
6. Control & BMS Wiring :
⇒ Terminate low-voltage wiring for:
- Remote start/stop
- Chilled water pump interlock
- Temperature and pressure sensors
- Alarm signals and status
⇒ Use shielded cables and proper segregation from power lines.
⇒ Integrate with BMS (BACnet/MODBUS/IP) for monitoring and load optimization.
7. Drainage & Slope
⇒ Provide floor drain nearby.
⇒ Chiller base shall have slope and a drain line connection.
⇒ For water-cooled units: condenser blow-down or drain provision is mandatory.
8. Bypass & Flow Provisions
⇒ Primary loop should have:
- Motorized 2-way/3-way valve
- Auto balancing valve or differential pressure controller
⇒ Ensure minimum flow rate is maintained through evaporator (use flow switch).
⇒ Install manual bypass during initial flushing/testing phase.
9. Commissioning Readiness
⇒ All sensors (Temp, Pressure, Flow) shall be calibrated.
⇒ Water quality testing done (pH, TDS, hardness).
⇒ System flushed, cleaned, and passivated.
⇒ Air venting and pressure testing of piping done.
⇒ Dry run of pumps and chiller before full load testing.
10. Tagging, Labeling & As-Built
⇒ Chiller model, capacity, refrigerant, and serial number plates must be visible.
⇒ All piping and cabling labeled as per project specs.
⇒ Provide as-built drawings, O&M manuals, and test reports post-installation.
Comments
Post a Comment